Milanovic: 60 months is currently the most realistic deadline for the subway, but no city in the world has avoided additional delays when executing such projects
Illustration (Photo: Dejan Aleksić)
– This year has already passed. The start should most likely be expected next year, meaning completion might occur in 2032 or 2033, provided everything goes smoothly. However, there isn’t a city in the world that hasn’t faced additional investments or interventions that extended the construction time – he pointed out.
Lot 3 entails the completion of stations and shafts following the passage of tunnel-boring machines, key tunnel sections - stretching from Pozeska Street, via the Banovo Brdo Park, Ada Ciganlija, and the Belgrade Fair, to the Mostar Interchange, the Sava Square, the Republic Square, Skadarlija and the Danube, mechanical and electrical installations, escalators and elevators, landscaping around the stations and shafts, and the testing and commissioning of all stations and sections.
Milanovic points out that the first phase of the Belgrade Subway’s first line involves the construction of 11 stations located at depths ranging from 10 to over 30 meters, along with three surface-level stations in the Makisko Polje area. He specifically highlights the subway station planned for Republic Square in the city center, noting that it is one of the most complex stations in the proposed subway system.
– First of all, this station is located in the very heart of the city, Belgrade’s historic core, and the construction site itself will occupy a vast area. This encompasses not only the Staklenac building but also the entire Zoran Djindjic Plaza and, I assume, part of the Vasa Carapic Park across from the Veterans Club Building. Essentially, a massive excavation, a hole, will be opened up: a rectangle 80 meters long, up to 50 meters wide, and over 30 meters deep – Milanovic explains.
He also reminds that valuable archaeological artifacts were discovered during the construction of the garage in Vlajkoviceva Street, near the National Assembly building, a project that has been ongoing for four years, and that, consequently, it can currently only be speculated about what lies beneath the surface of Republic Square.
– There is always a huge question mark regarding how things will proceed – he notes, emphasizing that while 60 months is the engineering estimate, the actual pace of the work remains to be seen.
The value of the contract for Lot 3 has not been disclosed, but Milanovic points out that the subway systems are extremely expensive projects and that some estimates suggest the first phase of the Belgrade Subway’s first line, from Makisko Polje to the Pancevo Bridge, will cost no less than EUR 3.5 billion.
Companies:
JKP Beogradski metro i voz Beograd
Power Construction Corporation of China Limited Ogranak Beograd
Tags:
PUC Belgrade Metro and Train
Power China
Dušan Milanović
Belgrade Subway
construction of Belgrade Subway
first Belgrade Subway line
Lot 3 of first line of first phase of Belgrade Subway
subway station Republic Square
Mostar Interchange
Republic Square Belgrade
Belgrade Fair
Sava Square Belgrade
Comments
Your comment
Naš izbor
Most Important News
Full information is available only to commercial users-subscribers and it is necessary to log in.
Pratite na našem portalu vesti, tendere, investicione projekte, grantove i pravnu regulativu.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno,
uz konsultacije sa našim ekspertima.

Izdanje Srbija
Serbische Ausgabe
Izdanje BiH
Izdanje Crna Gora