Railroad from Zemun Polje to EXPO complex – Works at several points on both route and overpasses
Source: eKapija
Thursday, 18.09.2025.
11:46
Thursday, 18.09.2025.
11:46
Construction site of new railroad near Nikola Tesla Airport (Photo: B. Petrović)
Works have been carried out at several points on the route of the future rail line from both the Zemun Polje and the National Stadium directions for some time now. Specifically, in the area of the Zemun Polje station, work on the overpasses, or viaduct, which is the future connection of this station with the rest of the future rail route, has progressed considerably, and earthworks have also progressed regarding the rail route before and after these overpasses. To connect the new railroad to the existing one at the Zemun Polje station, let us remind, the outer tracks were used, so trains coming from the direction of the airport will merge into track 1, while trains heading towards the airport will be separated from the existing right guard track.
There’s a similar situation in the opposite direction (National Stadium), where work is also being carried out at several points - the future rail route through the Srem plain, but also on the future overpasses.
As a reminder, a few months ago, the Government of Serbia also adopted a decision establishing the public interest in the expropriation of land and buildings in the territory of Belgrade, for the purpose of building a rail line that would connect Zemun Polje and the future National Stadium in Surcin. This decision referred to the first stage of construction, on the section from Zemun Polje to the location of the National Stadium, in accordance with the General Regulation Plan for Rail Systems in Belgrade.
In addition to the rail line, the construction of stations, overpasses, culverts and infrastructure installations - gas pipelines, electricity and heating networks, water supply, as well as transmission lines - is also planned. One of the locations where work has also been underway for a long time is the location of the future Surcin rail station.
(Photo: Dejan Aleksić)
This line, as has been announced several times, will be fully electrified with the most modern equipment and will be exclusively for passenger traffic. There will be six very demanding engineering structures on the section of the line.
When it comes to the railroad and highway crossing, there will be a bridge construction between the airport interchange and the Belgrade (Dobanovci) interchange.
In the airport zone, let us remind, the railroad stop will be about 500 meters away from the entrance to Terminal 1.
As for the National Stadium station, it will be the only real station on the route, with four tracks.
The idea is that in the future the railway will continue from there to Obrenovac.
The main contractor is the Chinese company Power China.
D. A.
Companies:
Power Construction Corporation of China Limited Ogranak Beograd
A.D. Aerodrom Nikola Tesla Beograd
Tags:
Power China
EXPO 2027
Belgrade Nikola Tesla Airport
Zemun polje EXPO Nikola Tesla Airport railroad
Zemun polje
Comments
Your comment
Naš izbor
Most Important News
Full information is available only to commercial users-subscribers and it is necessary to log in.
Pratite na našem portalu vesti, tendere, investicione projekte, grantove i pravnu regulativu.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno,
uz konsultacije sa našim ekspertima.

Izdanje Srbija
Serbische Ausgabe
Izdanje BiH
Izdanje Crna Gora