The section includes the route from km 67+680.41 to km 81+476.86, with a length of 13.79 km, with a connection to the State Road IB No. 24 via the graded intersection “Vrba” in Zaklopaca near Kraljevo.
Also, a work application certificate was issued to the City of Kraljevo for the regulation of the Balaban stream at km 68+664.58 and the Klican stream at km 70+977.08, in Zaklopaca.
The planned start date of the works specified by the investors in the application is December 8, 2025, and, as stated, the works can begin after the publication of this certificate.
Let us remind that, last week, Serbian President Aleksandar Vucic announced on his Instagram account that a 14.3-kilometer section of the Morava Corridor from Vrnjacka Banja to Vrba would be opened a few days later.
The total length of the Morava Corridor, the highway that will connect Kraljevo, Krusevac, Vrnjacka Banja and Trstenik, is about 110 km.
The corridor consists of three sections - Pojate-Krusevac (27.83 km), Krusevac-Adrani (53.88 km) and Adrani-Mrcajevci-Preljina (30.66 km).
The construction of the corridor began in late 2019 and is being carried out by the Turkish-American consortium Bechtel Enka. The road is designed for speeds of up to 130 kilometers per hour and, as announced, will be the first digital and widest highway in Serbia.
As we wrote last month, the state has borrowed an additional EUR 260 million for the construction of this corridor, and this is a loan agreement with the guarantee of the British agency UKEF.
See also our info-map Construction of Highways and Expressways in Serbia and the Region.
B. P.
Lokacija:
Google Maps
Companies:
Ministarstvo građevinarstva, saobraćaja i infrastrukture Republike Srbije
Koridori Srbije d.o.o. Beograd
Grad Kraljevo
Tags:
Ministry of Construction Transport and Infrastructure
Corridors of Serbia
City of Kraljevo
Zaklopača near Kraljevo
Balaban stream
Klican stream
Morava Corridor
Pojate Preljina highwway
Vrba Adrani subsection
graded intersection Vrba
certificate of application for works
beginning of construction
Comments
Your comment
Most Important News
Full information is available only to commercial users-subscribers and it is necessary to log in.
Pratite na našem portalu vesti, tendere, investicione projekte, grantove i pravnu regulativu.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno,
uz konsultacije sa našim ekspertima.

Izdanje Srbija
Serbische Ausgabe
Izdanje BiH
Izdanje Crna Gora