Turkish investor launching construction of Serbia’s largest solar power plant – 300 MWp package including new project
Source: eKapija
Friday, 11.09.2026.
11:05
Friday, 11.09.2026.
11:05
Illustration (Photo: Samuel Faber)
Multi-year administrative processes have been completed, permits obtained, land rights secured, and grid connection agreements finalized, officially moving the investment into the equipment procurement and construction phase.
Established facility and new project in portfolio
In addition to the well-known “Nocaj” mega-project - set to become Serbia’s largest solar power plant - the company has used this announcement to publicly unveil the “Green” project for the first time.
Read more:
- EBRD ready to finance construction of Serbia’s largest solar power plant with capacity of 270 MWp – Works near Sremska Mitrovica to begin in third quarter
- Turkey’s Fortis Energy receives permit to build 36 MWh battery system for SPP Nocaj 1 in Sremska Mitrovica – Installation to begin in Q2
- Serbia starts construction of one of largest solar parks in Europe – Fortis contracts construction of Nocaj 1 near Sremska Mitrovica
- Sremska Mitrovica to get one of largest solar power plants in Europe – Turkish Fortis Energy to start construction in spring
The total generation capacity the Turkish investor is launching in Serbia amounts to 300 MWp:
– Nocaj Solar Power Plant (270 MWp) – the cornerstone of the investment, located in Sremska Mitrovica (near the village of Drenovac). This project will also integrate a massive battery energy storage system (BESS) with a capacity of 72 MWh. Commercial operation is scheduled for the second quarter of 2028.
– Green Solar Power Plant (30 MWp) – this project is scheduled to come online much sooner, as early as the fourth quarter of 2027. The exact location has not been disclosed.
Together, these two facilities will supply more than 368 GWh of clean electricity annually to the domestic grid.
Battery system and domestic grid stabilization
The installation of the 72 MWh energy storage system at Nocaj is part of the “Green Baseload” strategy. Batteries will store excess solar energy during the day and discharge it during the evening peak in consumption. This directly addresses the issues of price volatility and the stability of the Serbian power grid, transforming variable solar energy into stable, baseload power.
This investment is part of a broader plan by Fortis Energy, a company whose development portfolio in Serbia already includes five solar power plants and four wind farms.
Albania included in same investment package
This wave of investment in Serbia is part of a larger package comprising 375 MWp of solar capacity and 112 MWh of storage that Fortis is developing across Southeast Europe. The remainder of the investment is located in Albania, where construction is commencing on the Erseke solar power plant (75 MWp), featuring a 40 MWh battery system. Across the region (Serbia and Albania), the facilities will supply approximately 494 GWh of green electricity annually - enough to meet the consumption needs of 141,000 households - and reduce CO2 emissions by 317,000 tons per year.
Branislava Petrovic
Companies:
Fortis Energy and Construction doo Beograd
Tags:
Fortis Energy
Noćaj solar power plant
Green solar power plant
electricity battery storage
biggest solar power plant in Serbia
construction of solar power plants
Comments
Your comment
Most Important News
Full information is available only to commercial users-subscribers and it is necessary to log in.
Pratite na našem portalu vesti, tendere, investicione projekte, grantove i pravnu regulativu.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno,
uz konsultacije sa našim ekspertima.

Izdanje Srbija
Serbische Ausgabe
Izdanje BiH
Izdanje Crna Gora