Data Center Planned in Beli Potok Near Belgrade Bypass - Environmental Impact Assessment Request Submitted

Source: eKapija Thursday, 23.07.2026. 10:42
Comments
Podeli
Plot in Beli Potok where the data center will be built (Photo: Print screen/Geosrbija)Plot in Beli Potok where the data center will be built
Belgrade-based company Cetin d.o.o. has submitted a request to the Serbian Ministry of Environmental Protection for a decision on whether an environmental impact assessment is required for a project involving the construction of a standalone commercial telecommunications center - data center in Beli Potok.


The project involves the construction of a building with B+GF+1 (technology section) and GF+2 (administrative section), on a 7,242 m2 plot in Beli Potok, Kruzni put Rakovica, Vozdovac Municipality, Belgrade.

The plot is located within the scope of the Detailed Regulation Plan for the commercial zone in Bubanj Potok, between the bypass and the planned railway line, within commercial zone K3.

Access to the plot where the data center will be built is planned from Nova 5 Street, while after the construction of Nova 1 Street, access from that street will also be possible and is envisaged.

The planned total gross floor area of the building is 3,986.95 m2.

The complex includes the main data center building, two transformer stations, a platform for diesel-electric generators, underground fuel storage tanks, a fire hydrant water tank and supporting infrastructure.

The facility is planned to have eight data halls and six employees. The facility's maximum electrical power demand will be 3.6 MW, while a note states that the project will not be a source of high-frequency electromagnetic radiation.
Šta imamo u krugu od:
1 km
2 km
3 km
5 km
10 km
15 km
Opis:
Projekat se odnosi se na izgradnju objekta spratnosti Po+P+1 (tehnološki deo) i P+2 (administrativni deo), na parceli površine 7.242 m2 u Belom Potoku, Kružni put Rakovica, Opština Voždovac, Beograd.Kompleks obuhvata glavni objekat data centra, dve trafostanice, plato za smeštaj dizel-električnih agregata, podzemne rezervoare za skladištenje goriva, hidrantski rezervoar i prateću infrastrukturu.

U objektu je planirano osam data sala i rad šestoro zaposlenih. Maksimalna angažovana električna snaga objekta iznosi 3,6 MW, a u napomeni se navodi da projekat nije izvor elektromagnetnog zračenja visokih frekvencija. (2026)
Vidi sve
Comments
Your comment
Full information is available only to commercial users-subscribers and it is necessary to log in.

Forgot your password? Click here HERE

For free test use, click HERE

Pratite na našem portalu vesti, tendere, investicione projekte, grantove i pravnu regulativu.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno, uz konsultacije sa našim ekspertima.