Preparations for new gold mine in Serbia: Canadians hauling dismantled equipment from Bulgaria to Coka Rakita

Source: eKapija Sunday, 12.07.2026. 11:55
Comments
Podeli
(Photo: iurii/shutterstock.com)
The Canadian international mining company DPM Metals Inc. (Dundee Precious Metals) announced in its latest quarterly report that processing equipment from the Ada Tepe mine in Bulgaria would be dismantled and used to develop the Coka Rakita gold project in eastern Serbia.

According to the company’s official statement, the ore processing plant at the Ada Tepe site will end its operations on July 15, 2026, after the last blasting was carried out in mid-April. Following the closure of this mine, the company is starting the process of dismantling and overhauling specific parts of the processing facilities in order to adequately prepare them for installation at the Coka Rakita project in Serbia.


The company’s management confirms that the construction of the Coka Rakita mine is expected to begin in early 2027. The use of existing infrastructure and proven technological equipment from the Ada Tepe site aims to optimize costs and reduce operational risks during the upcoming development of the project in Serbia.

At the same time, the company emphasizes its commitment to responsible reclamation and closure of the Bulgarian mine in accordance with European environmental standards, where it plans to return 95% of the land to the Natura 2000 nature protection network after restoration.

In the same business report for the second quarter of 2026, DPM Metals records stable financial results at the global level, driven by increased gold equivalent production at the active Chelopech mines in Bulgaria and Vares in Bosnia and Herzegovina.

Financial stability and the ongoing share buyback program, worth over USD 49 million during the past quarter, provide a solid foundation for further capital investments and development projects in the Balkan Peninsula, the company said in a statement.

The company’s official, complete operating and financial results for the second quarter will be formally presented to the public after the stock exchange closes on July 30, 2026.

B. Petrovic

Šta imamo u krugu od:
1 km
2 km
3 km
5 km
10 km
15 km
Fotografije:
Opis:
Procena je da će tokom radnog veka rudnika od 10 godina biti iskopano 1,2 miliona unci zlata ili oko 34 tone.

Prostorni plan će obuhvatiti delove teritorija opštine Žagubica (deo KO Laznica - Selište i deo KO Žagubica) ukupne površine 8.670 ha. Proizvodni kompleks budućeg rudnog ležišta (oko 280 ha) nalazi se unutar Planskog područja, odnosno istražnog prostora Čoka Rakita (1.393 ha) na području KO Laznica-Selište, delu sliva reke Lipe, pritoke reke Veliki Pek. Zona mogućih uticaja rudarskih aktivnosti obuhvata delove KO Laznica – Selište, KO Žagubica i KO Jasikovo (opština Majdanpek). Najbliža naselja rudarskom kompleksu su Laznica, Jasikovo i Žagubica (oko 10 km).

Orudnjenje se nalazi na dubini između 250 m i 560 m ispod površine terena. Maksimalna dužina orudnjenja po padu iznosi oko 340 m. Ležištu će se pristupiti putem dva niskopa od površine terena. Preovlađujući metod eksploatacije koji će se koristiti je metod otvorenih otkopa primenom dubokih minskih bušotina. Postrojenje za flotaciju planirano je da se izgradi na oko 1 km severno od vrha Čoka Rakita. (2025)
Vidi sve
Investicije na lokaciji:
Comments
Your comment
Full information is available only to commercial users-subscribers and it is necessary to log in.

Forgot your password? Click here HERE

For free test use, click HERE

Pratite na našem portalu vesti, tendere, investicione projekte, grantove i pravnu regulativu.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno, uz konsultacije sa našim ekspertima.