Biggest thermal power plant in Serbia to have its combustion system reconstructed – TENT must reduce pollution in order to continue working
Source: eKapija
Thursday, 11.09.2025.
10:57
Thursday, 11.09.2025.
10:57
TENT (Photo: Shutterstock/Baloncici)
This pertains to the modernization of the boiler, which was installed by the RAFAKO company back in the 1980s, in order to improve energy efficiency, extend the life cycle of the facility and considerably reduce harmful gas emissions.
The planned works entail the installation of eight new jet coal combustors with a low NOx emission, the introduction of two new levels of jets for additional combustion (OFA1 and OFA2), as well as the replacement of the current air mix canals, secondary and cooling air canals, de-clinker facility, compensator and ash funnels. All the works will be carried out within the existing facility, without changing its dimensions.
The new system envisages for the emission of nitrous oxides to be lowered to below 200 mg/m3 (at O2=6%), which is in line with the regulations of the European Union and the obligations from the National Emission Reduction Plan (NERP). As a reminder, NOx concentrations in combined waste gases of both blocks B1 and B2 amounted to 403 mg/m3, which is more than twice as much as the proscribed threshold.
The modernization of the boiler at the block B2 is a continuation of the process of harmonizing the operations of the thermal power plants of EPS with the European environmental standards, which is a prerequisite for their continued operations past 2027. The project is expected to secure fully controlled combustion with a greater degree of usage, as well as a considerable reduction of the negative impact on air quality.
TENT B, with two blocks with an installed power of 2x665 MW, is one of the pillars of the stability of the electrical energy system of Serbia. Annually, more than 11 million tons of the Kolubara lignite is combusted at the power plant.
I. Z.
Opis:
Vidi sve
Tags:
Elektroprivreda Srbije
TENT
Thermal Power Plant Nikola Tesla B Obrenovac
Ministry of Environmental Protection
reconstruction of combustion system and replacement of parts of pipe system of boiler at block B2 of Thermal Power Plant Nikola Tesla B in Obrenovac
reconstruction of combustion system
Comments
Your comment
Naš izbor
Most Important News
Full information is available only to commercial users-subscribers and it is necessary to log in.
Pratite na našem portalu vesti, tendere, investicione projekte, grantove i pravnu regulativu.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno,
uz konsultacije sa našim ekspertima.

Izdanje Srbija
Serbische Ausgabe
Izdanje BiH
Izdanje Crna Gora