Battle for Serbian cubic meters and kilowatts – 2024 Retrospective, investments in ENERGY AND UTILITY INFRASTRUCTURE
Source: eKapija
Tuesday, 28.01.2025.
08:22
Tuesday, 28.01.2025.
08:22
HPP Djerdap secures a fifth of the electricity produced in Serbia (Photo: Katarina Stevanović)
1. Last year’s Retrospective
That our people also felt a chill about this topic is also shown by the fact that our most widely read energy-related article last year, with figures like a minor scandal in a reality show, was – the retrospective of investments in energy in the previous Year of our Lord! As if, just to be on the safe side, we fear that this summer could be the last (warm) one. And the topic in that article, after the great energy crisis – after we turned EPS on a spit – was all-encompassing, from the construction of the RHPP Bistrica as a national priority – it never got started – to the oil pipeline to Hungary – we would need it now – and the hydroelectric power plant on the Ibar River, for the construction of which we founded a company back when Tadic was in power.
In addition, here is what our people wanted to read, for now under an (energy-saving) light bulb and from a municipal source of electricity:
2. Djerdap 3 – Bucharest won’t hear our pleas
Romania rejected the construction of Djerdap 3! The people who have a saying that in their neighborhood they have the Black Sea and Serbia as their friends, equally respect their own interests, and so we hear from the Romanian populace and the senate that a new, reversible Djerdap in the Serbian hills – would reduce the flow to the Romanian turbines. For us, on the other hand, it would be a gigantic energy storage facility for the times when we need it the most. Will Bucharest hear our pleas?
3. Gasification of Cyprus
And then, surprisingly, the news that a Chinese consortium had terminated the contract for the construction of the first terminal for the supply of natural gas to Cyprus attracted a lot of attention. We were worried, apparently, about the Cypriots – that they not go to the opposite side (the one that is supplied with gas by ships), although there is water all around Cyprus, like around a ship. Serbia has not managed to go down to the blue sea to have its own LNG terminal like Croatia, and experts say that in principle there is enough gas and that it can arrive via Hungary, but at what price?
Illustration (Photo: SpaceKris/shutterstock.com)
4. Closing Serbian thermal power plants
The process of finally closing two domestic thermal power plants got the bronze medal – as if, God forbid, we feel a little sorry for those toxic plants... that have been heating our stoves for decades with cheap electricity during the night, although we have never systematically solved the issue of heating bathrooms. At the end of the year, however, a new possibility emerged – a chance for a second life for these already mourned facilities: the Kolubara and Morava thermal power plants could burn biomass.
Illustration (Photo: akitada31/Pixabay)
5. Germans financing green hydrogen in Serbia
Green hydrogen – an ecological fuel that is produced in an environmentally sustainable way – is emerging as a favorite in the attempt to save the world through energy transition. The planet is slowly cooling down from its enthusiasm for electric cars of the Musk type, those with lithium batteries, and the powerful industry is increasingly looking towards electric cars that get their electricity from hydrogen fuel cells. And that means that fuel would be poured at gas stations again. The German government has decided to finance a pilot project for the production of green hydrogen in Serbia, and the HyDSerbia project will be implemented by Leipziger Energiegesellschaft. The beginning is planned modestly and as a “pulse-check”, and the ambition is to eventually establish green hydrogen installations throughout Serbia.
6. Azerbaijani gas is not like Russian
Given the large differences in quality and chemical composition between Russian and Azerbaijani gas - and the fact that we have previously only had experience with Russian imported gas - the company Transportgas Srbija doo from Novi Sad has commissioned a study on gas blending in the transport system. Azerbaijani gas comes to us via Bulgaria, and it is possible that some view this as another stab in the back from our neighbors and Western powers (and from Azerbaijan?); However, President Vucic was not at all happy when, at the beginning of this year, he announced that Azerbaijan was forced to stop gas supplies to Serbia for technical reasons - fortunately, the drama turned out to be unnecessary and a different kind of gas is once again coming to us from the Caspian Sea.
7. Hyundai investing in Serbia’s “solar gigawatt”
In October, the South Korean giant Hyundai announced that it would soon sign a contract with the Serbian government to build 1 gigawatt of solar power plants in our country, which was soon done. In the field of renewable sources, after (old) hydroelectric power plants and the first EPS wind farm, the state will thus take a big step into solar energy. The start of the construction of state-owned solar power plants is announced for the end of this year or the beginning of next year.
Illustration (Photo: Pixabay.com/lukasbieri)
8. No new RES power plants to be connected
The spring news that the connection procedures for power plants using variable renewable energy sources are being postponed due to the identified risk to the safe operation of the power system and the lack of reserves for system balancing caused great attention, especially among our professional subscribers. To clarify, the Serbian Transmission System Development Plan for the period from 2023 to 2032, determined that the maximum RES capacity that the system can balance is 5800 MW (4800 MW in wind power plants and 1000 MW in solar capacities), which means that not everyone will be able to sell electricity from solar and wind power plants...
9. Novi Sad-based investor changing laws of physics
Nikola Tesla announced in 1900 that gravity could be used to start machines, and I made it practical, researcher and inventor Veljko Milkovic, a member of the Serbian Academy of Inventors and Scientists (SAIN), said in an interview for eKapija. In his patented two-stage mechanical oscillator, the output energy produced is 12 times greater than the input, and the laws of physics, as we were taught, say that the input energy must be greater. But this additional energy does not come from nothing, but from gravity. Can Serbia use the inventions and patents of this inventor from Novi Sad?
Illustration (Photo: Dominik Vanyi/unsplash)
10. Radljevo open-pit mine – Coal until 2085
And until green energy takes root – stick to coal, Serbs! The Serbian Electric Power Company has submitted a request to the relevant Ministry for a decision on the need for an environmental impact assessment for the facilities of the first phase of the industrial and infrastructure zone of the “Radljevo Sever” open-pit mine. Radljevo is, in fact, the youngest open-pit mine in the Kolubara basin. Exploitation was supposed to begin in 2022, but the procurement of equipment was delayed. In the next six decades, this mine should provide up to 13.5 million tons of coal per year, announced President Vucic. That was a roundabout way of telling us until when we intend to use coal as an energy source.
M. Radonjic

We invite you to see which investments marked the year 2024 in the fields of AGRICULTURE AND FOOD INDUSTRY, ECOLOGY, TRANSPORTATION, SPORTS, TRADE CENTERS, REAL ESTATE, TELECOMMUNICATIONS AND IT, INDUSTRY, HEALTHCARE and TOURISM, ENTERTAINMENT AND RECREATION.
Companies:
Elektroprivreda Srbije ad Beograd
Tags:
2024 Retrospective
Retrospective Energy
Đerdap 3
construction of Đerdap 3
natural gas
LNG
LNG terminal
earth gas
gas pipeline
TPP Morava
TPP Kolubara A
closing of thermal power plants
closing of two thermal power plants
green hydrogen
production of green hydrogen
green hydrogen in Serbia
Azerbaijani gas
mixing of gas
state solar power plants
Hyundai
connection of power plants
Veljko Milković
two stage mechanical oscillator
Serbian Academy of Inventors and Scientists
SAIN
Radljevo open pit mine
Comments
Your comment
Naš izbor
Most Important News
Full information is available only to commercial users-subscribers and it is necessary to log in.
Pratite na našem portalu vesti, tendere, investicione projekte, grantove i pravnu regulativu.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno,
uz konsultacije sa našim ekspertima.

Izdanje Srbija
Serbische Ausgabe
Izdanje BiH
Izdanje Crna Gora