All four Kostolac-based thermal blocks will start operations as of December 1

Source: Novosti Tuesday, 26.08.2014. 14:03
Comments
Podeli
In the Kostolac Thermal power plants and mines revitalization works on block B1 which is to join EPS network again in late November, are in progress. About 1000 workers, 600 of them from China, are working on this overhaul. The overhaul of this block with the power of 350 MW, where a total of USD 112 mil is invested is the first stage of the credit line with China which comprises construction of the new desulphurization system of the Danube quay and industrial lane.

The second stage starting in late December 2019 comprises construction of the new thermal block and capacity expansion of the Drmno pit mine from 9 to 12 million tons of coal annually.

Apart from B1, block A1 is being overhauled which means that electricity in Kostolac is now produced with decreased capacities since only A2 and B2 blocks operate and they produce some 12.000 MWh of electricity for EPS daily.


- In the first half of August, these two blocks produced 145.000 MWh which exceeds this period’s plan regardless of fulfillment of the requests of the electrical and energy system for technical minimum during the night – Zoran Stanojevic, head of the Directorate for electricity production in TE-KO Kostolac, says for Novosti.

As of September 15, Block A1, undergoing overhaul at the moment, will produce electricity, with the power of 100 MWh.

- Block A1 was halted July 18 when the preparation works for capital overhaul started. They should end in September. Due to floods in May this year, technical reliability of the thermal facility must be on higher level because we have ahead of us the winter period during which not all EPS capacities will operate – Dusan Grubetic, lead engineer for turbo generator facility maintenance, says.

Block A2, with 210 MWh will start overhaul September 1 and will be operational again in a month. Block B2 was overhauled for 22 days, starting June 18 and then rehabilitation of generator and transformer replacement was carried out by Polish Alstom together with the local maintenance workers. Taking into account overhaul works and their dynamics, all four Kostolac-based thermal blocks will be put into operation starting December 1 when they will again produce some 15% of total electricity which EPS delivers to its consumers.

Comments
Your comment
Full information is available only to commercial users-subscribers and it is necessary to log in.

Forgot your password? Click here HERE

For free test use, click HERE

Pratite na našem portalu vesti, tendere, investicione projekte, grantove i pravnu regulativu.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno, uz konsultacije sa našim ekspertima.