Energoprojekt Niskogradnja and Colas Rail to lay down tracks on Ada Bridge – Tram traffic to open no sooner than in July 2019
Preliminary design for tram tracks on the Ada Bridge
The Belgrade Land Development Public Agency reached the decision to award the contract worth RSD 1.97 billion (around EUR 16.4 million) to the group of bidders consisting of Energoprojekt Niskogradnja and France’s Colas Rail.
As the document states, the completion deadline period is 420 days from the possession of the site. Ideally, then, tram traffic on the Ada Bridge will open in July 2019 if there are no complaints by any of the parties that have not been awarded the contract. If there are, however, it could postpone the construction and maybe even invalidate the tender.
The other two offers were sent by Austria’s Strabag and the group of bidders headed by the Spanish company Copisa.
Let us remind that the previous tender fell through in 2017, as the Belgrade Land Development Public Agency had deemed neither of the three bids to be acceptable.
Companies:
JP Direkcija za građevinsko zemljište i izgradnju Beograda
Energoprojekt Niskogradnja a.d. Beograd
Tags:
Colas rail
Strabag
Copisa
Altuna
Bauwesen
Geoas
Ad Bridge
tram tracks on Ada Bridge
tram traffic on Ada Bridge
Comments
Your comment
Most Important News
Full information is available only to commercial users-subscribers and it is necessary to log in.
Pratite na našem portalu vesti, tendere, investicione projekte, grantove i pravnu regulativu.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno,
uz konsultacije sa našim ekspertima.

Izdanje Srbija
Serbische Ausgabe
Izdanje BiH
Izdanje Crna Gora