Missing substation halts construction of Russian windmills – Raising of EUR 100 million wind farm near Boljevac late
(Photo: ekapija.com)
The head of the Municipality of Boljevac, Nebojsa Marjanovic, confirmed this for Novosti.
– The test have shown that, thanks to a favorable wind rose, a cost-effective wind farm might be built in the Boljevac area. The construction of a 100-MW wind farm is planned, but the works are yet to start. The reason is that a substation between Boljevac and Sokobanja, where the Russians might connect to our power system, has not yet been built.
Marjanovic notes that he expect the substation to be built fairly soon, so that the Russians might start implementing the investment, which would provide the municipal budget with around a million euros a year.
Six years ago, the Italian company Bondcom Green Energy from Modena was authorized to build a wind farm in the said municipality, but failed to do so, as it turned out that dealers had bought out the land in the targeted location and asked for an amount far above the market value.
Dissatisfied with this, the Italian company withdrew and the Russian investors bought the land, performed all the studies and acquired the permits.
Companies:
Opština Boljevac
Tags:
Boljevac wind farm
wind power
renewable energy sources
RES
production of electricity from wind
production of electricity
electricity
electrical energy
Nebojsa Marjanovic
Comments
Your comment
Most Important News
Full information is available only to commercial users-subscribers and it is necessary to log in.
Pratite na našem portalu vesti, tendere, investicione projekte, grantove i pravnu regulativu.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno,
uz konsultacije sa našim ekspertima.

Izdanje Srbija
Serbische Ausgabe
Izdanje BiH
Izdanje Crna Gora