Construction start on the track in Bela Reka tunnel at Corridor 11

In the
Bela Reka tunnel, at the Resnik–Valjevo section of the Belgrade-Bar railroad,
which is a part of the European traffic Corridor 11, works on the track installation have started with usage of elastomer carpet technology, it was
written in the RZD’s announcement
As they
state, this technology has already been recognized in the world and now, they
outline, for the first time it has been implemented within railways
modernization in Serbia.
Tunnel, more
than 3,8 km long, was built in 1958 and it has not been renovated since then.
RZD International started reconstruction of the facility in December 2016 and during that time, they say, works on water effluents from tunnel walls and reconstruction of its invert have been done.
After
replacement of rail field, device and contact network, train speed increased
from 50 to 120 kilometres per hour, the company states.
Works on
the reconstruction of the Resnik–Valjevo section, they state, have been in
progress in line with the Annex 4. 1 with the Contract signed by RZD
International and Infrastruktura zeleznice Srbije in December 2015.
Planned deadline for project implementation is, they state, June 2018, and its contracted value totals app. USD 80 m.