Energoproject agrees on new business of USD 50 m in Belarus
Friday, 09.10.2015.
11:50
Capacities of gas and turbine facilities with supplementary electric and mechanical equipment are - production of electricity 16,4 MW, heat energy for heating of complex 30 MW and cooling energy for the needs of cooling of 15,2 MW.
Commitments comprise project management, development of the main design, construction and architectonic works, procurement and delivery of entire equipment and material, assembly of mechanical and electrical equipment, testing and release and development of technical documentation and as-built drawings.
Works total USD 50.055.282. Deadline for project completion is 23 months.